Hi Jishu,
You have to specify in the parameters for the order confirmation (OPK4) that the activity sequence is supposed to be checked. In that operation sequence set as error when operation sequence is not adhered to
Also you have to define relation between those Phases FS (Finish - Start) in master recipe.
Regards,
R.Brahmankar