Why you cannot change setting of your factory calendar and declare holiday for Week ends & on Public holidays.
Or
Manually calculate days falling under week ends & public holidays, then add these days with needed possible delivery date and then enter TOTAL REQUIRED DELIVERY date in material master.Now create PO and extra days will be added as additional delivery date.
Regards,
Biju K