Hi Dave,
Thanks for reply please find the below steps performed.
- Goods receipted with 2 items A1(Quantity200), B1(Quantity50) and Mat.Doc1 gets created at MIGO-->Two Documents one for each item updated in work list shows OK.
- 2.GR Cancelled for both Items A1(200) B1(50) of Mat doc1 at MIGO -->Work list updated both the created documents(Mat doc 1) are not available shows OK.
- 3.GR created for item A1(200) B1(50) at MIGO and Material doc2 created -->Two Material Documents one for each item updated in work list shows OK.
- 4.GR cancelled for only Item A1(200)-->Work list updated accordingly shows only one Mat doc2 with Item B1( 50) Works OK.
- After few hours GR cancelled for item 2 B1(50) -->the Mat doc2 document still appears in the work list.Not working as expected.
Note:- If we do cancellation of goods receipt is works fine but when we do after few hours the material document still shows in the work list.
Thank you